End of construction works for the hoisting tower of the "Janina VI" shaft

On the investment related to the construction of the final surface and underground infrastructure together with the mining shaft hoist of the “Janina VI” shaft, works related to the reinforced concrete structure of the main structure – the hoist hoist are coming to an end. In addition, facade panels made of sandwich panels are being installed, and the first installation works inside the buildings have started. The main structural works of the headroom building have been completed and assembly works of the crew building platform are coming to an end. In addition, external networks, roads, squares and narrow gauge railways are also being built.